What Is a Performance and Payment Bond in Construction?

A performance and payment bond is a two-part surety guarantee used in construction: the performance portion guarantees the project owner that the contractor will finish the job as agreed, and the payment portion guarantees that subcontractors, laborers, and material suppliers will be paid. Federal law requires them on government construction contracts over $150,000, and most states impose similar requirements on public projects at their own thresholds.

How the Bond Actually Works

A surety bond is not insurance, and confusing the two leads contractors into expensive mistakes. Insurance is a two-party deal in which the insurer absorbs covered losses. A P&P bond involves three parties:

  • Principal: the contractor who buys the bond and whose obligations it backs.
  • Obligee: the project owner or government agency that requires the bond and is protected by it.
  • Surety: the bonding company that issues the bond and steps in if the contractor defaults.

When the surety pays a claim, it collects that money back from the contractor. Every contractor signs a General Agreement of Indemnity before a bond is issued, and that agreement typically requires the business owners personally, and often their spouses, to guarantee repayment. The surety can pursue personal assets, not only company assets, to recover what it paid out. The bond protects the owner and the trades working under the contractor. It does not protect the contractor.

Performance Side vs. Payment Side

The two bonds are almost always issued together but cover different risks for different people.

Performance Bond

This one protects the project owner. If the contractor walks off, goes bankrupt, or delivers work that fails to meet contract specifications, the owner files a claim against the performance bond. The surety can then finance the original contractor to finish, hire a replacement, or pay the owner the cost of completion up to the bond’s limit.

Payment Bond

This one protects the people working under the contractor. Subcontractors, laborers, and material suppliers who aren’t paid can file directly against the payment bond to recover what they’re owed. On public projects this protection matters even more, because unpaid parties cannot file mechanics’ liens against government-owned property.

The Penal Sum

Every bond has a “penal sum,” which is the maximum the surety will pay on claims. On federal construction contracts, the Federal Acquisition Regulation sets both the performance bond and the payment bond at 100 percent of the original contract price. A $2 million contract carries a $2 million penal sum on each bond. If completion costs or unpaid invoices exceed that cap, the surety’s obligation stops there and claimants have to pursue the contractor directly for the rest. When change orders increase the contract price, the government can require the contractor to raise the bond amount to match.1Acquisition.GOV. FAR 52.228-15 Performance and Payment Bonds-Construction

When These Bonds Are Required

Federal Projects

The Miller Act, at 40 U.S.C. §§ 3131–3134, requires performance and payment bonds on federal construction contracts.2Office of the Law Revision Counsel. 40 US Code 3131 – Bonds of Contractors of Public Buildings or Works The statute sets the threshold at contracts exceeding $100,000, and the Federal Acquisition Regulation implements mandatory P&P bonds on contracts over $150,000. For federal contracts between $35,000 and $150,000, the contracting officer chooses an alternative form of payment protection, such as an irrevocable letter of credit or escrow, instead of a full payment bond.3Acquisition.GOV. FAR 28.102-1 General

State and Local Projects

Nearly every state has a “Little Miller Act” mirroring the federal requirement for state- and locally funded construction. Thresholds vary widely, from as low as $25,000 to as high as $500,000. Check the specific state statute before bidding on any public work.

Private Projects

No law forces private owners to require P&P bonds, but many do on large or complex jobs to shift the risk of contractor default onto the surety. Lenders financing private construction often require them as a condition of the loan.

What Happens When Something Goes Wrong

If the contractor fails to perform, the owner notifies the surety and files a claim on the performance bond. The surety investigates, and if the default holds up, it picks the cheapest workable resolution: funding the original contractor to finish, hiring a replacement, or paying the owner the cost of completion up to the penal sum.

Payment bond claims run on a separate track. Unpaid subcontractors or suppliers file directly with the surety, which reviews invoices, contracts, and lien waivers before paying valid claims. On federal projects, the Miller Act sets hard deadlines: every payment bond suit must be filed within one year of the claimant’s last day of work or final material delivery, and subcontractors who did not contract directly with the prime must first send written notice to the prime within 90 days of that last day.4Office of the Law Revision Counsel. 40 USC 3133 – Rights of Persons Furnishing Labor or Material Miss the one-year deadline and the claim is gone. State Little Miller Acts run their own notice periods and filing windows, which often differ from the federal rules.

Whatever the surety pays, the contractor owes back. That is what the indemnity agreement is for.

Getting Bonded and What It Costs

Surety companies underwrite on three factors, often called the three Cs: capacity to handle the project’s size and scope, capital to support the work financially, and character shown through a record of completed jobs and paid obligations. Underwriters look at credit history, financial statements, work-in-progress schedules, bank relationships, and references. Larger contracts typically require audited or reviewed financials plus personal financial statements from the owners.

Premiums are a percentage of the contract amount. Contractors with solid credit, strong financials, and a completion track record generally pay 1 to 3 percent, so $10,000 to $30,000 on a $1 million contract. Weaker credit, less experience, or thin balance sheets push the rate higher and can require posted collateral. Project complexity, tight deadlines, and unfavorable payment terms also affect the price. On federal projects, bond premiums are generally reimbursable as a contract cost, so the government effectively pays for the bond. On private work, the contractor absorbs the cost or builds it into the bid.

The SBA Surety Bond Guarantee Program

Newer and smaller contractors often can’t qualify for bonds on the projects they want to bid. The U.S. Small Business Administration’s Surety Bond Guarantee Program addresses that by guaranteeing a portion of the surety’s risk, which makes sureties willing to issue bonds they would otherwise decline. The program covers contracts up to $9 million for non-federal work and up to $14 million on federal contracts where a contracting officer certifies the guarantee is necessary.5U.S. Small Business Administration. Surety Bonds For a small contractor trying to enter bonded government work, the program is often the practical way in.