What Is a Bond Claim? Filing Steps, Notices & Deadlines

To file a bond claim, identify the surety bond covering the project, send written notice of non-payment within the deadline that applies to your tier (90 days from your last work on a federal Miller Act project, often shorter on state projects), submit your documentation to the surety company, and if the claim is denied or ignored, file suit against the surety before the statutory cutoff — one year from your last day of work on federal projects. The timeline is strict: miss a deadline by a day and the claim is gone, regardless of how much you are owed.

Most of what follows applies to payment bond claims, which are by far the most common. Performance bond claims — made by project owners when a contractor abandons or botches a job — follow a similar structure but involve different claimants and different remedies.

Confirm You Have the Right to File

Not everyone on a job site can make a bond claim. Under the federal Miller Act, which governs bonds on federal construction contracts over $100,000, protection reaches only the first two tiers below the prime contractor. First-tier claimants contract directly with the prime. Second-tier claimants contract with a first-tier subcontractor. Anyone further down the chain — a supplier to a supplier, for example — has no Miller Act claim no matter how large the unpaid balance.1Office of the Law Revision Counsel. 40 U.S. Code 3133 – Rights of Persons Furnishing Labor or Material

State bonding laws — commonly called Little Miller Acts — govern state and local public projects, and every state has one. The dollar thresholds and tier rules vary. Some states require bonds on projects as small as $25,000; others set the floor at $100,000 or more. Check the specific statute before assuming you qualify.

Private projects are a different animal. No law forces a private owner to require bonds, so when a bond does exist on a private job, its terms come from the bond document and the underlying contract rather than from a statute. Read the bond itself — notice requirements, protected parties, and deadlines may bear no resemblance to the Miller Act. On private work you usually also have mechanic’s lien rights as a backup, which do not exist against public property.

Step 1: Find the Bond

You cannot file against a bond you cannot identify. On federal projects, any subcontractor or supplier who has furnished or been asked to furnish labor or materials can request the surety’s name and address from the contracting officer, and can request a certified copy of the payment bond itself (the agency may charge a reasonable copying fee).2Acquisition.gov. FAR 28.106-6 Furnishing Information

On state and local projects, procedures vary. Some states record the bond in public records. Others require a written request to the awarding authority. On a private project with a bond, the bond is usually attached to or referenced in the subcontract — your contract file is the first place to look.

Step 2: Send the Required Notice

This is the step that kills more claims than any other.

Under the Miller Act, a first-tier claimant — someone who contracted directly with the prime contractor — does not have to send any preliminary notice before suing. A second-tier claimant must send written notice to the prime contractor within 90 days of the last day they performed labor or supplied materials.1Office of the Law Revision Counsel. 40 U.S. Code 3133 – Rights of Persons Furnishing Labor or Material The notice must identify, with reasonable accuracy, the amount owed and the party you worked for or supplied.

Use a delivery method that creates third-party proof of receipt. Certified mail with return receipt is standard. Email and phone calls will not save you if the surety later denies that notice was ever delivered.

State bond statutes often require notice regardless of tier, and the deadlines can be shorter. Some require preliminary notice within 30 or 60 days of first furnishing labor or materials — meaning the clock starts when you begin, not when you finish. Pull the statute for your project and calendar every date the day you learn of the problem.

Step 3: Build Your Documentation

The surety is going to look for gaps, so assemble the file before you submit. Pull together:

  • Your signed contract or purchase order
  • Itemized invoices showing dates of labor or delivery
  • Proof of delivery — signed receipts, bills of lading, delivery tickets
  • Daily work logs or timesheets for labor performed
  • All written correspondence about the payment dispute
  • Photographs, inspection reports, and expert assessments if defective work is in play

The strongest claims trace a clean line from the contract to the work performed to the invoices to the non-payment. If you cannot show that materials were actually delivered or labor was actually performed, the surety will stall the claim while asking for more.

Step 4: Submit the Claim to the Surety

Send the claim directly to the surety company — not just to the contractor. Include a cover letter that identifies the bond number, the project, the prime contractor, and the total amount claimed, and attach everything from Step 3. Use a delivery method that generates a receipt.

Sending the demand to the contractor alone is not a bond claim. The surety is a separate party and must be notified on its own.

The Deadlines That Control Everything

On federal Miller Act projects, three dates matter, and all three run from the same event: the last day you furnished labor or materials to the project.

  • 90-day notice window (second-tier claimants). Written notice to the prime contractor must go out within 90 days of your last work or delivery. First-tier claimants are exempt from this requirement.1Office of the Law Revision Counsel. 40 U.S. Code 3133 – Rights of Persons Furnishing Labor or Material
  • 90-day waiting period before suit. You cannot file a federal payment bond lawsuit until at least 90 days have passed since your last work. The window exists to let the contractor and surety try to resolve the claim short of litigation.
  • One-year suit deadline. The lawsuit must be filed no later than one year after your last day of work or delivery. Courts have dismissed claims filed a single day late.1Office of the Law Revision Counsel. 40 U.S. Code 3133 – Rights of Persons Furnishing Labor or Material

You have a narrow corridor: no suit before 90 days, no suit after one year. On a long project where you supplied materials over many months, pinning down the exact last day of delivery is critical and worth confirming in writing with the party you worked for.

State deadlines run on their own clocks and are frequently shorter. Some states allow as little as 60 days for preliminary notice and six months for suit. Do not let the contractor’s assurances about payment “next month” burn through your filing window.

Where to File Suit

Miller Act lawsuits must be filed in the United States District Court for the district where the contract was performed.1Office of the Law Revision Counsel. 40 U.S. Code 3133 – Rights of Persons Furnishing Labor or Material Federal courts have exclusive jurisdiction; state court is not an option. The complaint is filed in the name of the United States for the claimant’s benefit — a procedural requirement worth getting right.

Claims on state and local bonds generally go to state court. Private project bond claims follow whatever dispute resolution procedure the bond or contract specifies, which may include arbitration. Filing in the wrong forum wastes time you likely do not have.

What the Surety Does With Your Claim

Once the surety has your claim, it opens an investigation. Expect the surety to review your contract, the bond, and your supporting documents, contact the prime contractor for a response, and request additional information from you. On performance bond claims the surety may visit the site.

The investigation evaluates whether the claim is valid, whether notice requirements were met, whether the claimant qualifies as a protected party, and how much is actually owed after back-charges, disputed change orders, and incomplete work. Sureties have an independent duty to investigate rather than simply deferring to the contractor’s account.

If the surety finds the claim valid, it will typically push the contractor to resolve the payment directly. If that fails, the surety pays the claimant and then pursues the contractor under the indemnity agreement the contractor signed when the bond was issued. That indemnity right is why a bond claim has real consequences for the contractor — the surety will seek reimbursement, and repeated claims can make a contractor unable to secure bonds for future public work.

If the surety denies the claim, it issues a written explanation. The usual grounds are a missed notice deadline, insufficient documentation, the claimant falling outside the protected tiers, or a factual dispute over the work. Denial leaves the claimant with one path: file suit against the surety within the applicable deadline.

Defenses to Expect

Blown deadlines are the surety’s cleanest defense. A late notice or a late lawsuit will draw a motion to dismiss regardless of the merits of the underlying debt. Courts enforce these dates strictly.

Pay-if-paid clauses in subcontracts are the next recurring issue. If the subcontract conditions the prime’s obligation to pay on the prime receiving payment from the owner, some sureties argue the condition passes through to the bond claim, since the surety’s liability cannot exceed the principal’s. Enforcement varies sharply by state. Some states enforce these clauses; some have struck them down as against public policy; others enforce them only if the clause uses specific condition-precedent language. Ambiguous clauses are usually read as pay-when-paid provisions, which affect only the timing of payment and not the obligation itself.

Sureties also challenge the claimant’s performance — arguing the work was defective, the materials did not meet specification, or the claimant did not comply with the contract. Clean delivery receipts and signed inspection approvals make these defenses hard to sustain, which is the reason documentation matters so much at the submission stage.

Watch Lien Waivers Carefully

As a project progresses, you will be handed lien waivers or claim releases to sign in exchange for payment. These documents can waive your right to file a bond claim, not just a mechanic’s lien. Read what you sign.

Conditional releases take effect only when payment actually clears. Unconditional releases take effect the moment you sign, whether the money arrives or not. Signing an unconditional release before confirming the funds have cleared your account is one of the costlier mistakes in construction. Many states have statutory forms for these releases, and some void any release that does not follow the prescribed format. For progress payments, sign conditional waivers; sign unconditional waivers only after the deposit has cleared.