Construction escrow is an arrangement where the money for a building project sits in an account controlled by a neutral third party, and that third party only pays the contractor, subcontractors, and suppliers after each stage of work has been documented and verified. The point is simple: the owner isn’t writing checks for work that hasn’t happened, and the contractor isn’t performing work with no assurance the money exists. The escrow agent, usually a title company or a bank, is bound by a fiduciary duty to follow the written escrow instructions and cannot take sides.
Who’s Involved and What They Do
Four groups show up in almost every construction escrow. The owner funds the account and carries the ultimate financial responsibility for the project. If the project is financed, the lender controls disbursements because the building is its collateral. The general contractor runs the work on the ground and submits the paperwork that triggers each payment. Subcontractors and material suppliers sit at the end of the payment chain; they usually don’t sign the escrow agreement itself, but they depend on it to get paid for what they put into the job.
The escrow agent is the neutral in the middle. The agent holds the funds, checks the documentation, orders the inspections, confirms title, and releases money only when the conditions written into the escrow agreement have been met. Because no single party controls the account, no single party can force a payment or block one without going through the agreed process.
What Goes Into a Draw Request
Money doesn’t leave the escrow account on request. It leaves against a documentation package, and most delays in construction escrow trace back to paperwork that doesn’t line up.
The Schedule of Values
At the start of the project, the contractor submits a schedule of values alongside the signed construction contract. It breaks the contract into line items for each phase of work: foundations, framing, electrical, plumbing, and so on. Every future draw request references these line items and reports what percentage of each is complete. The escrow agent uses the schedule to make sure no single phase gets overpaid in a way that would leave the budget short later.
The Sworn Statement
Every draw request is anchored by a sworn statement, sometimes called a contractor’s affidavit. It lists each subcontractor, supplier, and laborer on the job and shows, for each one, the total contract amount, what has been paid, what is being requested now, and the balance remaining. Requirements for the format and content vary by state. What doesn’t vary is that the numbers have to match the construction contract and the schedule of values. If they don’t, the escrow agent will send the draw back.
Lien Waivers
A lien waiver is the document in which a party acknowledges payment and gives up the right to file a mechanic’s lien against the property for the covered amount. There are four standard versions: conditional on progress payment, unconditional on progress payment, conditional on final payment, and unconditional on final payment. The conditional versions take effect only once the payment actually clears. The unconditional versions take effect the moment they are signed, whether or not the check ever arrives. A contractor should never sign an unconditional waiver before confirming funds are in hand. The escrow agent collects waivers from everyone who was paid on the prior draw before releasing the next one.
How a Payment Cycle Runs
Once a complete package is in the escrow agent’s hands, the cycle follows a predictable sequence.
The contractor submits the draw request, either through a digital portal or by delivery. The escrow agent arranges a site inspection by a third-party inspector who visits the project to confirm that the percentage of completion claimed in the paperwork matches the work actually in place: materials on site, labor performed, line items progressing against the schedule. Inspections typically run between $179 and $550 per visit, depending on the project.
After the inspection clears, the agent orders a title search update, sometimes called a date-down. This pulls the current public records to check whether any new mechanic’s liens, judgments, or other encumbrances have been filed against the property since the last disbursement. A new lien appearing between draws stops the payment until it’s resolved.
With inspection and title confirmed, the funds move. Wire transfer is the common method; some agents still issue corporate checks. The whole sequence, from draw submission to payment released, generally takes one to three weeks, and it runs faster when the first submission is clean.
Retainage: How Much Is Held and When It’s Released
Retainage is the slice of each progress payment that the owner or lender holds back from the contractor until the project reaches a defined completion milestone. The purpose is leverage: keeping money in reserve gives the owner reason to expect the contractor will finish the punch list and close out the job properly. Most construction contracts set retainage between 5% and 10% of each payment. The broader trend has been toward 5%, because higher percentages put real financial pressure on subcontractors who may wait a long time to see that money.
Retainage rules on private projects vary significantly by state. A growing number of states cap the holdback at 5% of the contract price; others still permit up to 10%. Several states now require retainage to be released within 30 to 60 days after substantial completion or final acceptance, with interest penalties for owners who miss the deadline. Rates and enforcement differ, so the state’s construction payment statute controls the specifics on any given private job.
The release trigger is almost always substantial completion, which means the project is finished enough that the owner can occupy or use it for its intended purpose. Final completion comes later, after every punch list item is resolved and the remaining contract obligations are met. The last piece of retainage is released at final completion.
What It Costs, and Where the Interest Goes
Construction escrow is not free. The escrow agent charges administration fees for setting up and running the account, processing each draw, coordinating inspections, and ordering title updates. These fees are negotiated as part of the escrow agreement. The owner or lender usually pays them, though on some projects the cost is split or built into the contractor’s price. Most providers quote on a case-by-case basis rather than publishing a rate sheet, so getting a written fee schedule before signing is worth the time.
One detail catches a lot of owners off guard. Interest earned on funds sitting in the escrow account typically belongs to the escrow agent, not to the party who deposited the money. Standard escrow agreements let the agent hold funds in its general accounts with no obligation to invest them for the depositor’s benefit. On a large deposit, this is real money. If you want the interest, you have to negotiate an interest-bearing arrangement into the escrow agreement before signing, because it won’t happen by default.
If sworn statements or lien waivers need to be notarized, notary fees run from about $2 to $30 per signature depending on the state, with most falling between $5 and $10. Mobile notaries who come to the job site add their own travel charge on top.
When the Owner and Contractor Disagree
The escrow agent’s duty is to follow the written instructions, not to decide who’s right. When the owner and contractor fight over a draw — the owner says the work is defective, the contractor says the inspector was unreasonable — the agent will typically freeze the disputed amount and wait for the parties to reach agreement or for a court to order a release. The agent has no authority to mediate.
If the standoff doesn’t break, the escrow agent can file an interpleader action, which asks a court to take custody of the disputed funds and decide who gets them. That protects the agent from being sued for paying the wrong party, but it adds legal cost and delay neither side wants. The practical lesson is upstream: the escrow agreement itself should spell out exactly what documentation triggers a release, what counts as a valid objection, and what timeline applies before the agent is authorized to act. Disputes that reach interpleader usually started with vague escrow instructions.
Backstops When Escrow Isn’t Enough
Construction escrow is one layer of payment protection. Two others operate alongside it, and they matter whether or not an escrow account exists.
On private projects, a contractor or supplier who goes unpaid can file a mechanic’s lien against the property. The lien attaches to the title in the public record, which makes it hard for the owner to sell or refinance until the debt is cleared. If the lien stays unpaid, the lienholder can ultimately force a foreclosure sale. Filing deadlines vary by state and can run from a few months to two years after work is completed. The structured draw process and lien waiver requirements in a construction escrow are specifically built to keep these liens from being filed in the first place, because the escrow agent won’t release the next payment without confirming the prior round of obligations has been satisfied.
On federal construction contracts over $100,000, the Miller Act requires the prime contractor to post a payment bond guaranteeing that subcontractors and suppliers will be paid even if the prime defaults. The bond amount must equal the contract price unless the contracting officer finds that impractical, and it can never be less than the performance bond amount.1Office of the Law Revision Counsel. 40 USC 3131 – Bonds of Contractors of Public Buildings or Works Mechanic’s liens can’t be filed against government property, so on federal work the payment bond is the primary safety net for unpaid parties. Many states have their own “little Miller Acts” imposing similar bond requirements on state and local public projects.
Federal projects also run under the Prompt Payment Act, which requires the government to pay an approved progress payment within 14 days of the request or owe interest on the late amount, and requires prime contractors to pay subcontractors within 7 days of receiving federal payment or owe interest at the same rate.2Office of the Law Revision Counsel. 31 USC 3903 – Regulations3Office of the Law Revision Counsel. 31 USC 3905 – Payment Provisions Relating to Construction Contracts This flow-down rule reaches every tier of subcontracts on a federal job.